| Title and Location |
Brief Description |
| Dungeness ‘B' Power Station |
Structural integrity check to latest BSs for 70m high dumbbell shaped building housing two nuclear reactors, various associated mechanical plant, cranes, fuel handling gantries etc. Structural steel framed building with some concrete floors and some steel beams with concrete slab construction. A major project with a very high level of professional responsibility. All work carried out to Kashec's third party certified QA system |
| Dungeness ‘A' Nuclear Power Station |
Independent checks of repair and strengthening proposals to prove safe operation into the new millennium, including independent assessment of primary bioshield walls and pilecap to resist increased operational requirements |
| Berkeley Power Station |
Survey and detailed design of protective deck, demolition and new roof as part of the height reduction scheme of the decommissioning process. Included design of external bases to support boiler shells. |
| Bradwell Power Station |
Prepare schemes for the proposed decommissioning of the power station. Carry out design for the schemes and prepare drawings. Schemes looked at the ways of reducing the size of the existing reactor buildings etc. |
| Sizewell ‘C' abnormal load route |
Assessment of heavy load route including bridge assessments, carriageway restriction surveys, overhead obstructions, extensive report and review of heavy transport options available. |
| Oldbury Power Station |
Assessment of capacity of turbine loading bay for plant and abnormal transporter loads. |
| Civil Inspection at Bradwell Power Station |
Assist in carrying out inspection of the power station buildings to identify defects and prepare database. |
Ling AO – Nuclear Power Station |
Redesign of condensate polishing plant according to new layouts including concrete frame, cladding and foundations |
| Wylfa Nuclear Power Station |
Preparing safety case for hot gas release scenarios. Checking adequacy of number of structural elements. |
With our considerable experience in the Nuclear Industry we are well equipped to advise the client on complex issues relating to the safety case regarding civil engineering matters. We have prepared a number of reports which have been used in preparing safety cases for various aspects of the power station's continued operation. We have had experience of dynamic seismic analysis and design. Design checks for bioshield and pilecap subjected to large thermal variations were also undertaken independently. Independent checks of design, calculations and drawings prepared by others were also carried out on some projects.
We have strong capability for developing pre and post processing software for any finite elements analysis using commercial programmes where considerable output data is generated.We have written in house, appropriate customised software for such applications for Dungeness A and other projects which have allowed us to rapidly check the result from the FE output.